![]() |
. | |||||||||||||||||||||||
![]() |
||||||||||||||||||||||||
|
|
||||||||||||||||||||||||
|
Building Envelope Remediation at the Sunset Pond Apartments
|
||||||||||||||||||||||||
|
The Sunset Pond Apartments consist of 140 units in 2 eight-unit 2 story buildings, 5 twelve-unit 3 story buildings and 4 sixteen-unit four story buildings. Exterior Research and Design, LLC provided a summary specification, details, and to provide contract administration. Western Exterior Service, Inc. was engaged as the general contractor initially to perform limited work during the development of the specification and subsequently to carry out the work to the entire project. The project manager was Mark Reichlin. The Superintendent was John (Jack) Kuljis. Gary Swenson SE. of Swenson Saye Faget Engineering provided analysis and recommendations for repairs to the wood frame structure were excessive damage had occurred. XXXXX. was engaged by the mortgage lender to provide third party oversight and financial review.
Project Overview
The project consisted of; removal of all vinyl siding and house wrap installation of a new Weather Resistive Barrier (WRB), window flashings, transition flashings, and vents. The original siding was reinstalled along with new trim materials.
Project Challenges
Maintaining Access for Tenants Through-out the Project: The original specification was developed to replace the surfaces in like kind. Walkway repairs were specified as for removal of the concrete walkways, installation of new waterproofing, and pouring new concrete topping. The tenants ability to access their units would be severely disrupted while carrying out this work. Emergency Exiting: A Building Access and Emergency Egress Plan was developed and implemented. The plan was not a permit requirement, but was implemented nevertheless to provide a base point for continued training of our staff on the importance of tenant access during working hours and during hours that we were not on site. Previous Repairs: The stair towers were reconstructed the prior year. The facias, hand rails and waterproofing of the walkways transition to the prior repair. Lender Participation: The owner had been unable to refinance due to the building defects and the pending litigation. The spread between the original, and current market for interest rates was significantly affecting the cash flow from the properties.
Technical Challenges
Hardscape Transition at the First Floor Sidewalks: The concrete was poured up against the vinyl siding at some locations. Stair Stringer Transitions to Waterproof Surfaces: The existing stair- stringers transitioned to the new waterproofing, and facias. Flashing to the wood stringers was technically difficult. Ventilation of the Walkways: The Bellingham fire department would not allow vent penetrations through the lid of the walkways. Walkway Slopes and Post Supports: The walkways were supported by a rim attached to the building at one side and by posts and beams at outside. The multi-floor buildings settled but the posts did not causing a reversal of the slope. Many of the walkways did not drain. |
||||||||||||||||||||||||
|
Contact Us. Email : markr@exteriorservice.com |
||||||||||||||||||||||||
|
||||||||||||||||||||||||