Project |
Seattle Christian Schools |
|
Title |
Big Day's Work |
|
Primary Subject |
Framing Repair |
|
Secondary Subject |
Interior Protection |
|
Secondary Subject |
Scaffolding |
|
Secondary Subject |
Difficult Schedule |
|
Secondary Subject |
Owners Participation |
![]() |
The south wall of the high school was the last to be repaired, and time was running short.
|
| The inside was protected by floor covering and partitions.
|
|
![]() |
A large crew reframed the entire wall on a long
Saturday.
The school maintenance personnel also sacrificed
there weekends to accommodate the tight schedule.
|
| By lunch all of the studs but two were replaced In spite of working long our six days a week Jeff still manages to keep his hair neatly trimmed. |
![]() |
![]() |
Studs were cut off six at a time. The studs
were being replaced at one side, while studs were being
cut at the other.
The work resembled an assembly-line.
|
| The new sheathing and insulation went up after in the afternoon |
![]() |
![]() |
The long hours paid off. The last of the classrooms were ready for the students 49 days after the project began.
|