Village on the Green Phase I |
|
Title |
Hardscape Transition |
|
Primary Subject |
Hardscape Transition |
|
Secondary Subject |
Concrete transition to wood frame wall |
|
Secondary Subject |
Membrane Flashing at Concrete to Wood |
|
Secondary Subject |
Membrane and Sheet Metal Flashing |
|
Secondary Subject |
Cementitous and Membrane Repair |
![]() |
|
| Damage at hardscape transition |
|
![]() |
In some cases the EIFS extended bellow the concrete
|
| The concrete was filled with waterproofing cement |
|
![]() |
The transition is prepared for a membrane flashing application
|
| Membrane flashing is applied over a cementitous sealer |
|
![]() |
The membrane flashing extends up the wall and laps under the building paper
|
| Sheet metal with a hemmed bottom edge is installed to protect the membrane and improve the appearance |
|