Western Exterior Services, Inc.
|
Project |
Village on the Green Phase I |
|
Title |
Kickout Flashing |
|
Primary Subject |
Kickout Flashing (missing) |
|
Secondary Subject |
Missing Kickout |
|
Secondary Subject |
Damage behind EIFS |
|
Secondary Subject |
Roof EIFS Transition Damage |
|
Secondary Subject |
Damage 4 Years Old |
![]() |
|
| A simple flashing would have prevented the water entry by diverting the water into the gutter |
|
![]() |
The sheathing damage was severe, but the framing was not yet damaged
|
| Repairs were made to the sheathing and preventive treatment was applied to the framing |
|
![]() |
The problem was typical throughout
|
| The problem was typical throughout |
|
![]() |
The sheathing and the fascia required replacement
|
Next Village on The Green I Series